Lucent Technologies Miramar, FL
The Lucent Technologies Miramar Florida facility is a 4-story, 229,000 square foot computer research and
development complex. The mixed-use structure contains office spaces,
laboratories, computer rooms, UPS
rooms, mechanical rooms, a fitness
center and a full service kitchen.
Mechanical and electrical systems
were designed for full redundancy
and fail-safe operation. High-density
computer racks were arranged
in hot aisle/cold aisle configuration.
Leibert overhead cooling systems
were installed to cool the
aisles in addition to the conventional
underfloor systems.
Commissioning services included
design review, commissioning
specifications, construction inspection,
pre-commissioning checklists,
functional performance testing,
and failure mode testing for all critical
systems, Owner’s training and system
documentation.
Systems commissioned included
the central plant with water cooled
centrifugal chillers, cooling towers,
boilers, and emergency generators,
UPS systems, electrical distribution,
Liebert computer room air-conditioning systems, air-handling
units, DDC control system, pre-action
fire protection systems, lighting,
and VAV systems serving the
office areas.
The cost of construction was $140
million dollars.
Architect: Veenendaal Cave Inc.
Location: Miramar, Florida
Project Size: 229,000 sq. ft.
Construction Cost: $140 Million
Completion: 2003
Systems Commissioned: HVAC,
Central Plant,
Electrical,
Emergency Power,
UPS systems,
Fire Protection, and
Failure mode testing